hello guys, I’m not sure if this question have been asked but I already tried to find the answer but they are not what i am looking for. so i want to know if i can put the same task on multiple dates without creating additional task on my “all task” grid?


Unfortunately that’s not possible. Each item in a calendar view corresponds to a single record. To have something appear on multiple dates, you’ll need multiple records.

1 Like

Thank you so much. do you have any suggestion on how not to make the “all task” grid look like a mess?

Use views with combinations of grouping and/or filtering to control which records are visible. Not all records need to be seen all the time, so pick which ones you want to see and build views for those configurations.