Hello everyone! I’ve created a calendar view (with correct dates) and shared the link to my Google Calendar. For some reason, the entry in my Google calendar is displaying 1 day late. It should display today September 25th and instead, it’s September 26th!


Is your date field set to use GMT or not?

1 Like

Yes it is and the issue has been resolved. Thanks!