I need to ensure no dates in my base land on a weekend or holiday. I’m trying to use the WORKDAY(startDate, numDays, [holidays]) formula to accomplish this. However… issues. I’m using “0” as numDays since I do not want to add any days if the date already lands on a working day. This does not move the date however if it lands on a weekend or holiday. If I change numDays to “1”, then the date automatically moves forward a day, regardless if the original date already lands on a weekday. How can I resolve this? Is there a “if weekday” formula that I can add in?