I have a task table and some have linked records to a subtask table.
Is there a way to get the subtasks to show up on a timeline view page that the source is the task table?
If not, is there any other suggested way of managing subtasks that would allow this that isn't a long text with rich text checkboxes?
Thanks!
- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎Feb 13, 2025 05:28 PM
Hmm, perhaps an automation that'll help you create the subtasks in the tasks table automatically? I'm curious about your setup though, when faced with this issue I usually just display the timeline from the subtasks table instead:  
- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎Feb 14, 2025 06:55 AM
Hi Adam–
So I have tasks and some of them have subtasks but not all so as for as I can figure out I can't just point to the subtask table like you're showing in your screenshot.
Ultimately I'm trying to figure out a way to capture tasks AND tasks with subtask in the data to help track and timing and resources per project and individual. Started with the project management template and have been modifying if to what the team needs.
Using the rich text route creates the need for a lot of formula work to extract that info and have it roll correctly.
Having all the tasks on one table MIGHT be the way to go and then link them to the 'parent' task but I'm not sure how that would play out the predecessors.
Two separate tables seemed to be the right solution but maybe not.