Hi, I'm trying to build a project cost tracker but I'm reasonably new to airtable. The issue I'm having is that as the project evolves, the costs change (as requirements change etc.). The business wants to be able to see that variance. Currently, when costs change, a new cost estimate record is created. All are linked back to the opportunity (our proposal to the client). However, I can't think of how to calculate the cost variance by cost centre automatically.
An example of what I'm trying to achieve is below:
| Opportunity (LINKED TO RECORD WITH PRICE TO CLIENT) | COST CENTRE 1 | COST CENTRE 2 | COST CENTRE 1 CHANGE FROM THE PREVIOUS ESTIMATE | COST 2 CENTRE CHANGE FROM THE PREVIOUS ESTIMATE |
Cost Estimate V1 – Deal 1 | DEAL1 | £500 | £100 | N/A | N/A |
Cost Estimate V2 – Deal 1 | DEAL1 | £600 | £50 | £100 | -£50 |
Cost Estimate V1 – Deal 2 | DEAL2 | £200 | £200 | N/A | N/A |
Cost Estimate V2 – Deal 2 | DEAL2 | £300 | £200 | £100 | £0 |