I need formula where Due Date=Date of release + 6 workdays.
Please help! Thanks!

2 Replies 2

Hi @Nataliya_Bondarenko

This should do it for you:

WORKDAY(Date,6)

Note that you can also list Public Holidays after the number of days if you need to take these into account.

More information here.