I’m trying to set up a Gantt block (or possibly multiple Gantt blocks) displaying the timeline of tasks LEADING UP TO a goal date.
A project (record) will have tasks with predecessors, and I want to work backwards from the GOAL DATE, with the last task ending just before the GOAL DATE/TIME, and the preceding task ending just before that one needs to start, etc.
Can I plot multiple tasks, pertaining to the same record, on a Gantt block? Or, does each of these tasks need it’s own Gantt chart?