Hi! I would like to use the WORKDAY function to count the number of working days from an input date, but I would also like to include the input date as well.
For example, if I count 6 working days from 19-Aug, the WORKDAY formula would count until 27-Aug.
However, I want 19-Aug to be included in those 6-days – so by right, 6-working days from 19-Aug, including 19-Aug itself, should be 26-Aug.
How do I include that in a formula?
Thanks in advance for any help! :grinning_face_with_smiling_eyes: