Hello all, thank you so much for taking the time to read this, any help would be appreciated
I have a question with regards to a topic that Gareth covered in is "“Allocating Resources with a Timeline View”.
His demonstration is great, however the utilization field in the timeline only links to a single record, which is fine if you only take 1 day off at a time. My records need to have both a start and end, some up to a week apart.
My question, is there a formula, or other method that will allow to be take both of these dates and consolidate all of the dates in between into a single cell? As this seems to be the only way for the timeline to recognize all of my holidays
If there is a better solution for me to do this then any help is appreciated, but essentially the end goal is to find a way to combined projects and holiday data (2 dates) onto one timeline
Thanks !