I have been working with custom views to better filter my task list.

I am using the Collaborator option to assign tasks to my team. I would like to set up a view so that I can easily find all the tasks that are not assigned yet to anyone.

The view filter for the Collaborator field only lets me choose a collaborator to show, and I can’t find a way to show just the fields without a collaborator.

Any thoughts on how to do this?

Thanks,

4 Replies 4
Katherine_Duh
Airtable Alumni (Retired)

You can change the filter operator so that instead of saying {Fieldname} is [Collaborator name], it says {Fieldname} is empty.

11 PM

Not getting that option, Katherine. I think it is because I am using actual Collaborators rather than a pull down menu field.collaborator field.png

it's there.gif

Awesome Katherine! That worked. I was missing that I could change the IS to different options.