Help

Formula for percent progress marking tasks as Complete

Solved
Jump to Solution
1404 2
cancel
Showing results for 
Search instead for 
Did you mean: 
Mica_Fisher
4 - Data Explorer
4 - Data Explorer

Hi everyone,

I’m looking to create a Field where I can mark tasks as either “Complete”, “In progress”, or “Not started” based on the Percent Complete I have manually entered in another field.

I’m using this formula, and it’s working for everything except Complete:
IF({Progress} = 100, “Complete”, IF({Progress} = 0,“Not started”, “In process”))

I’m also including a screenshot. What am I doing wrong?

Screen Shot 2021-10-18 at 5.45.03 PM

Thanks!
Mica

1 Solution

Accepted Solutions
Kamille_Parks
16 - Uranus
16 - Uranus

Percent fields are stored as decimal values. So 100% isn’t 100 its 1.0. Therefore your formula should be:

SWITCH(
   {Progress},
   1, "Complete",
   0, "Not started",
   "In process"
)

or the following if you want to stick with nested IF()s

IF({Progress} = 1, "Complete",
IF({Progress} = 0, "Not started", "In process"))

See Solution in Thread

2 Replies 2
Kamille_Parks
16 - Uranus
16 - Uranus

Percent fields are stored as decimal values. So 100% isn’t 100 its 1.0. Therefore your formula should be:

SWITCH(
   {Progress},
   1, "Complete",
   0, "Not started",
   "In process"
)

or the following if you want to stick with nested IF()s

IF({Progress} = 1, "Complete",
IF({Progress} = 0, "Not started", "In process"))

Amazing, thank you!!!