Gantt fixed Finish-to-Start Dependency?

Topic Labels: Views
1024 0
cancel
Showing results for 
Search instead for 
Did you mean: 
Glenn_Fick
6 - Interface Innovator
6 - Interface Innovator

When I adjust a predecessor to end earlier, how do I get the successor to also start earlier? ie - how do i create a fixed finish-to-start dependency with a fixed amount if time between them? This is how every other gantt schedule program I’ve used does it ( ex. finish-start + 0 days )