Trying to make an interface with a “maximum possible spend” for each project launch day. Projects launch twice a week and run from 2 days to 15 days. I need to find a way to ask the question “Is this project still running next Tuesday” and “i...
Okay so I solved this one myself using multiple formulae.
I started with this. That let me calculate when next Tuesday/Friday is in a way that Airtable understands.
I then created the following formula:
IF({End Date} = BLANK(),"False",
IF(AND({Next F...