I set up my table with a Predecessor field (linked field back to the table). I’ve been using this to drive some calculations on dates for sequencing and showing in the Gantt chart. However I want to also use the successor for some other calculation...
I’m a bit swamped at the moment but I could walk you through it in a couple of weeks likely via a zoom call). It’s one of those things that started off simple and then got real complicated (mainly due to AirTable constraints on formulas, and I didn’...
Rose - thanks for the explanation. It’s a bit of a rabbit hole - i’ve created some calculations that will automatically adjust dates based upon some rules. e.g. When determining the calculated Start Date for a task … check if there’s a predecessor ...