Thanks @AlexLama, was trying to avoid having to create a record for each individual assignment to a resource but I think your recommended workaround is the cleanest way. I do have a quick follow up - is there any way to conditionally filter on the Ut...
@AlexLama Are there any workarounds for when you want to assign unequal work distribution? For example, if I have a project/task that takes 48 hours but want to split those hours 75% to one resource and 25% to another. Thanks!