Good morning,
I need to have a formula for my risk register which is based on the risk score with a number range.
If score is:
1-5: color is green
6-11: color is orange
12-25: color is red
I’ve come up with the following formula which technically wor...
Hi all, I’ve linked two tables and created dependencies between the two but I need to see this visually with connector lines showing the relationships between records from the two tables - Is there a way to view my dependencies with connectors line o...
In my table, I have many projects inserted as different records in a column. In another column, I included the project lead for each project, and in a third column are other staff members working on each project but are not project leads.
I want to c...
In my table, I have column 1 and column 2 with multiple select options for names. Column 1 has project leads (which include only senior managers) and Column 2 (which include both junior staff and senior managers).
I manually added names of junior sta...
Hi Mohamed,
I only see the dependencies on the gantt chart when they link to records within the same table. When I link a record as a dependency to one in another table it shows up in a separate dependency column created to link two tables together. ...
WilliamPorterTech:
each person to the projects
Hi William,
Your suggestions are really helpful. Thank you. You understood my issue. Sorry I wasn’t clear in my message - I meant workload as in the number of projects one person is working on at ...