Help

Date Dependencies / Gantt for tasks spanning less than 1 day

Topic Labels: Base design
96 1
cancel
Showing results for 
Search instead for 
Did you mean: 
Gunnell
5 - Automation Enthusiast
5 - Automation Enthusiast

I tried to search the community before posting and found this question (with no solution) several times, but the posts I found were pretty old so I just wanted to double check to make sure this was still impossible using Airtable alone.

I'd like to use the Date Dependency features to help with automatically shifting task and displaying in a Gantt chart. However, many of the tasks span less then one day. For example:

Task 1: Purchase Paint - Start 6/12/2024 - End 6/12/2024
Task 2: Paint Wall - Start 6/12/2024 - End 6/12/2024

I can't paint the wall until I purchase the paint, so I want to setup a dependency. But it doesn't take an entire day to purchase paint. When I setup Date Dependencies, the only option I have for creating a duration field is at the "day" level and setting dependencies means my tasks on the same day can't overlap. 

Am I missing something? Is there a workaround? Or is this still an issue?

1 Reply 1
Kyrstin_Graves
7 - App Architect
7 - App Architect

So I have managed to do this by setting the duration to 0 before I put in the start and end dates, it automatically updates the duration after you input the dates, but doesn't seem to move them. 

If that doesn't work out, they added a new logic to Date Depencies where for Gantt views, it can auto-reschedule as you drag if they overlap. If I understand correctly, setting it to None instead of Flexible should keep them from changing dates on you.