I am trying to create a timeline table to assist with tracking heavy volume days.
The first option once I choose to create a timeline- it gives me a drop down with several options.
"Using date range from (Due Date) to (Date Entered) **both ( ) fields are drop downs.
When I select those 2 options- i get the follow error message
" The above fields cannot be displayed because DUEDATE and Entered have configurations that are not compatible. "

What I am trying to do is create a “Puck” like timeframe where I can view all of our open work orders-
each one identified by a puck (bar) that runs from date entered to due date.
Any ideas as to how I can get the dates to communicate correctly?
I included a screenshot of the error message I am receiving.