Hello, my dear friends!
Has anyone found a friendly way to deal with having multiple tasks on the same day in Gantt view? The invalid dependencies are enough to drive anyone batty :stuck_out_tongue: , but I can live with that, what’s more difficult is sorting.
We are trying to use the Gantt view to communicate tasks to team members on the build floor and coordinate hand-offs. However, the Gantt view can be incredibly confusing, becasue everything is all out of order. Is there a way to sort same-day tasks that are dependent on each other, so they are always in successive order?
I did this in another base by creating 50 look up fields to look up the previous tasks task and so on, but that is a pain to recreate each time and will eventually break.
Thank you!!
p.s. same issue on timeline view