My Interface goals are stalled because I can not figure out how to create my desired bar graph. I created a bar graph example in R to show that I would like to have the number of hours on the Y and the dates on the X. They do not necessarily have to be color coded but they should be separated by the location. In my own attempts to create this bar graph I have only been able to create a count of the number of hours logged. For example, 2 hours has been logged twice for two different dates. This does not provide any substantial information on time and the number of hours spent traveling per location. If anyone is willing to help me figure out how to create this bar graph, please reach out! I would really appreciate it.
Solved! Go to Solution.
Accepted Solutions
- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎Jul 29, 2024 08:35 PM
Hmm how does this look?
 
 
- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎Jul 29, 2024 08:35 PM
- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎Jul 30, 2024 08:55 AM
Yes! How can I replicate this?
- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎Jul 30, 2024 08:36 PM
Once you duplicate the base to your workspace you'll be able to see all the chart settings!
- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎Aug 02, 2024 06:27 AM
Hello Adam.
I duplicated the base and still can not find the chart settings. My only option is to go to the three dots on the corner and print the chart. This does not allow me to see the chart settings.
- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎Aug 02, 2024 09:29 PM
Hm, could you provide a screenshot of your duplicated base with the Interface page open?
- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎Aug 08, 2024 09:41 AM
- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎Aug 08, 2024 10:27 PM
Ah, I see! You're looking at the published Interface, not the editor
Try clicking on the title and then clicking "Edit" afterwards:
I'd also suggest checking out the Interface docs on how to get started: https://support.airtable.com/docs/getting-started-with-airtable-interface-designer