Hello everyone !
I am sharing with you a « funny » problem that keeps my neurons busy and now depressed. If only I could :
Create a form where a Roll up could be displayed as a Single Select in a formSelect existing records through a form & update th...
One of the most common dependency in reverse planning is actually Start to Finish.I have a Milestone, set at a date D, I need to do a task ... and that task needs to be finish before the milestone starts.In the end, it's the entire scope of relations...
With the help of Scottworld, I have taken the following path :slightly_smiling_face:
Hello @Someone !
I have eventually gone the way described below.
I am only sharing the backbone of my tables, I added many other extra fields & automations to ease...
Thank you very much for your answer @ScottWorld !
I indeed went through your first path, my issue is that with timeslots, it adds a number of fields in the possibilities to pick from. But hey! I’ll just deal with it (I added a formula which returned ...