Hello, I am trying to see if I can do some higher level (and automated) KPI tracking using Airtable. See the following image:
Here’s what I want to stop doing manually: Tracking per month “Job Completions”.
For some background, I have the “Schedule”...
In a Grid View, how would one filter out tasks that are only “Ongoing” as seen in the Gantt Chart? The tasks have a start and stop date, and I want to show only tasks that should be currently happening. This will help eliminate distractions of future...
Thanks for the swift reply. Here’s the list with a filter set to show only “Ongoing”
It seems to be only tasks with Due Dates only, which I use as milestones on the gantt chart. Looking at it now, I think this mechanism adds complexity since for the...