I have this working partly with make.com and airtable together. What you need to do is connect each task and lookup the finished date. Then when that is filled in add one day to it to schedule the start date of the next task. You should be able to do...
Airtable does have a `WORKDAY()` function that allows you to calculate a date that is a certain number of workdays from a start date, excluding weekends (Saturday and Sunday) and, optionally, a list of dates that should be excluded (such as holidays)...
Yep, i am doing this right now. What you need to do is add a check box to lock in the date. Then filter out any records with the box checked from the automation hitting them again.