Can I have a setting that when I add subtasks for them to automatically have the start and end date of the task they belong to?
Solved! Go to Solution.
Accepted Solutions

- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎Oct 21, 2021 11:40 AM
If you have a table with your tasks and a table with your subtasks and they’re linked together, you could use 2 lookup fields for start and end date (and if you need it, use an automation to add those dates to 2 real date fields).

- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎Oct 21, 2021 11:40 AM
If you have a table with your tasks and a table with your subtasks and they’re linked together, you could use 2 lookup fields for start and end date (and if you need it, use an automation to add those dates to 2 real date fields).

- Mark as New
- Bookmark
- Subscribe
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎Oct 25, 2021 03:59 AM
Thank you! This will work. Appreciate it!