For the Gantt Chart view, does anyone know if there's a way to have airtable automatically adjust all dependent task start dates when the predecessor task is moved up (backward in time)?  

I see that airtable automatically pushes out all dependent tasks automatically (this is great) but if a task duration is shortened or end date is moved back, all of the dependent tasks stay exactly where they are. 

Is there a setting I need to turn on to enable automatic date adjustments in both directions?  This seems like a very basic feature for Gantt charts and doesn't quite make sense to have it only for updates in one direction but not the other! 