To whom it may concern,
An enhancement suggestion from Kalypso: When using the Date Dependencies settings, Start dates (And due dates if a Duration is already set), should auto populate when a Predecessor is selected.
Screen shot after having entered a Duration and selecting Predecessor.
Selecting View All for the 1 Invalid Dependency error and selecting Fix All has no effect. However, if I update the date in the Predecessor, or select a date in the dependent task, then the dates are displayed.
Here I changed the date in the Predecessor and the dates in the dependent task populate.
Here, (after undo), I have selected the start date of the dependent task.
Neither of those solutions should be necessary.
Expected Benefits: More efficient and less confusing data configuration process for project schedules that utilize Date Dependency features.
Please consider adding this capability.
Regards,
Jason Knighten