More mature dependency relationship options (Finish-to-Finish)

cancel
Showing results for 
Search instead for 
Did you mean: 
mattd
5 - Automation Enthusiast
5 - Automation Enthusiast
Status: New Ideas

Right now, it looks the Gantt view only supports Finish-to-Start

However, I'd like to be able to track Finish-to-Finish

The "workaround" to do this would be to further split by deliverable's final step that is actually dependent on the dependency. However, this generates a lot more data and linkage that makes the everything orders more difficult to both manage and digest

Start-to-Start is one I can find some use in, too, but Finish-to-Finish is very common

Smartsheets is capable of this and summarizes everything well here: https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors 

1 Comment
Sho
11 - Venus
11 - Venus

Good idea.
I think I need to set up Start-to-Start dependencies and Lag in my case.

It would be nice to be able to change the dependency settings to something other than Finish-to-Start.