Hello,
I’m looking for a way to track whether projects completed by team members were done so early, on time or late. I have a column that uses a single select drop down option for them to change their status when they proceed to the next portion of their project (On Deck, In progress, etc).
Is there a way that I can set up a formula to track when a task goes from one status to the other, compare the date it was changed to the due date (also set up in a column using the date field) and return a value of either early, on time or late?