I know that these types of questions have been asked several times here, but I haven’t been able to replicate suggestions from other threads to get the desired empty cell for my formula. Thanks in advance for any assistance!
My formula is:
DATEADD({Associated Event Date}, {Days before/after event date} * 1, ‘days’)
some of my tasks do not have a value for the {Days before/after event date} field. In these cases, I would like for the cell to show up empty rather than show #ERROR.
Please help :grinning_face_with_big_eyes:
Solved! Go to Solution.
Jun 10, 2021 03:18 PM
IF(
AND({Associated Event Date}, {Days before/after event date}),
DATEADD({Associated Event Date}, {Days before/after event date}, 'days')
)
Jun 10, 2021 03:18 PM
IF(
AND({Associated Event Date}, {Days before/after event date}),
DATEADD({Associated Event Date}, {Days before/after event date}, 'days')
)
Jun 10, 2021 03:52 PM
Thank you, that took care of it!