Hi! New user here, so probably doing something wrong.



I’m having a table of tasks, where tasks can have another row as a predecessor (“Follows” field). If it does, I want the start date of the task to be set to the day after the end of the previous task. But I don’t know how 🙂



Any ideas?



Thanks,


Stefan

I’m unfortunately not allowed to put images in a post here.



But I have a “Previous end” column that is a LOOKUP and fetches the “end” of the linked item in the “Follows” column.



End is a formula field and calculated by adding Duration to the Start column.


Start is also a formula field and calculated by IF({Follows}=BLANK(), {Earliest start}, WORKDAY({Previous end}, 1))



Earliest start is just a date field.



So, if “Follows” is set, we use “Previous end” + 1 day. If “Follows” would be set to the current row, it WOULD be a circular reference, by why is it now?