Hi there! I've been searching across the Airtable (AT) community for answers, and none so far.
I am trying to create a production schedule that has multiple dependencies across time. I followed the template that AT provided. I also included a new formula (found through the AT community) so that the End date is calculated by using the Start Dates and duration (Days it takes) for each task while excluding weekends. IF Formula below:
IF(AND({Start Date},{Days it takes}),WORKDAY({Start Date},{Days it takes}), {Start Date})
The Main Problem:
When I go into Gantt view, I am not able to click and drag on a task box to move the start and end date.
This shows up as one of the things mentioned that should be available in the Gantt View. I found it from "Working with records in the Gantt view" on Airtable:
"You can also adjust the dates that a record begins and ends (without changing its duration) by clicking and dragging the bar earlier or later on the timeline."
How do I solve this?
I would like to keep the former formula in my Grid view in order to keep the workday calculations I've made. Any suggestions are welcome!
Thanks.