How do I add risk management into a project? For example: I have a timeframe, and assign a risk, which gives me a pessimistic and optimistic view of time padded onto the start/end date. I’ve seen this in other tools, where it changes the color, so the center block is assigned, to the left is optimistic, and right is pessimistic.

2 replies

Jen_Rudd
Forum|alt.badge.img+15
  • Inspiring
  • September 23, 2021

So to manage the record, you can add a formula that will add # of days on each side based on risk. So a optimistic start and pessimistic end as a formula. That will give you the pad.

Showing up on the Gantt might be a little tricky, perhaps use the Vega block to visualize?


Forum|alt.badge.img+2
  • Author
  • New Participant
  • September 24, 2021

So to manage the record, you can add a formula that will add # of days on each side based on risk. So a optimistic start and pessimistic end as a formula. That will give you the pad.

Showing up on the Gantt might be a little tricky, perhaps use the Vega block to visualize?


Thanks that’s very helpful!