Hi Everyone,
My team and I are planning on migrating our Project Management tool to Airtable. We have more than 2000 tasks, among them ~500 tasks that have a multitude of dependencies. We appreciate the Gantt view showing those dependencies. Unfortunately we have so many dependencies that the dependencies on the Gantt view are hard to digest and to work on, particularly for those that are showing as “invalid”.
Is there a way to extract/highlight invalid dependencies into a separate table, view or even field? Or another solution (e.g. formula) to easily alert and/or track these invalid dependencies other than the red dotted arrows in the Gantt view?
Note that the flowchart app is not meeting our needs: app limited to 100 records, records’ timeline not taken into account, thus no option to highlight invalid dependencies.
Thank you in advance,
Lucas