Can I have a setting that when I add subtasks for them to automatically have the start and end date of the task they belong to?
Page 1 / 1
Hi @Dragana_Knezevic
If you have a table with your tasks and a table with your subtasks and they’re linked together, you could use 2 lookup fields for start and end date (and if you need it, use an automation to add those dates to 2 real date fields).
Hi @Dragana_Knezevic
If you have a table with your tasks and a table with your subtasks and they’re linked together, you could use 2 lookup fields for start and end date (and if you need it, use an automation to add those dates to 2 real date fields).
Thank you! This will work. Appreciate it!