Hi There!
I'm developing a resource allocation base for my team, where tasks may involve multiple collaborators, each with distinct daily availability and varying percentages of time commitment. While assigning resources at the project level is an option, it doesn't accommodate the differing daily time percentages required by each collaborator. How can I structure the template to effectively account for these variables?
Page 1 / 1
Hi Kevin,
Appreciate the response and the offer to design a POC. I just finished configuring another table that links to both ‘Tasks’ and ‘Collaborators’ and tracks their % Daily Time Required there. It worked!
Thanks again!