Hi, is Airtable able to do Finish to Start formulas that autofill dates similar to smartsheets? I’d love to have a sheet with the tasks and deadlines are autofilled based on the formula for how many days from Go-Live, so all I would enter is the Go-Live date and all tasks are automatically filled. Is this possible in Airtable?

1 Solution

Accepted Solutions

If you want a system where the end date for one task becomes the start date for the following task, you cannot do this in Airtable using formulas alone. It could be done with a custom script.

See Solution in Thread

1 Reply 1

If you want a system where the end date for one task becomes the start date for the following task, you cannot do this in Airtable using formulas alone. It could be done with a custom script.