Hello!
I just joined my company and I am entirely new to Airtable. I’m a project manager and I’m looking to use dependencies in my grid to automatically update my project schedule that I’ve created. For example, I’d like to make task B dependent on the conclusion of task A (finish-to-start relationship) AND, if I update the end date of Task A, the start date of task B should update based on the new end date of task A, as well as any other tasks on my schedule that are dependent on B and so on. I’ve figured out how to create dependencies but it doesn’t auto-update any of my dependent tasks when I update dates which is VERY manual and time consuming as a project manager. I’ve also noticed that Airtable only accommodates finish-to-start relationships and I often time need start-to-start relationships. Does anyone know if this functionality exists or if there are work-arounds?
I’m coming from a company that used Smartsheet for project management and I’m really struggling to equate the functionalities :frowning:
Thank you for your help in advance!