I am an artist that works with ceramics and have many repetitive tasks (each with several subtasks) that can take as little as 3 hours to complete and as long as 6 hours to dry... all dependent on the prior Task being completed on time. I created my first Gantt View. I entered both Start and End date fields with correct times for each of my tasks and I included dependencies.
When I view it as a Gantt chart it claims that the records are overlapping in time (they aren't). If I try to fix dependencies it pushes every single task to take a full day which makes the project 4x longer than it should be. My only logical conclusion is that the Gantt View is somehow completely ignoring the time data from the Date field and rounding to the nearest whole Day.
Surely there must be some setting I'm missing here. Any suggestions? I've been using the free version for some time and was considering upgrading to the pro for the Gantt Views. It would be hard to believe it would even be considered a Pro Feature without being able to handle more than one task in a day.
Thanks!