Hi - I’m trying to link a chronological set of tasks based on the completion date of a proceeding task. I’ve figured out how to project the due date by taking the start date plus Duration (in days) to get a projected due date, however, i’m stuck how to link this to the next record.
For example Task 1 is completed on 1/1/20
Task 2 should have a start date of 1/1/20 plus some duration (say 3 days) and have a projected due date of 1/4/20
Task 3 will then have start date of 1/4/20 and so on…
any help would be appreciated!