Hello,
I have run into a issue where a date field with time is adding an extra day to a timeline view. Here’s what I’m working with:
- Using a timeline for Resource Management Utilization
- Applied Summarize Utilization
- Using Available Hours
- Using Account for Time off
- The Start and End Date fields on the Timeline Date Fields and the Time Off Date Fields include time.
What I’m seeing:
- When an End Date on Time Off is set to any other time then 12:00am it marks the following day as also being Time Off (OOO).
-


I’ve tired every setting we have on the timeline view to fix this and nothing works. It makes absolutely no sense as to why it added an extra day. Does anyone have a fix for this or Airtable devs, can you please fix this?
Thanks!