Skip to main content

Adjusting Dates with Gantt Chart

  • September 8, 2020
  • 0 replies
  • 10 views

I’m looking at using a Gannt chart to adjust dates of projects as needed. If I drag dates further out, the tasks that are dependent on them move appropriately. If I then drag to an earlier date, the tasks that were dependent DON’T also move to an earlier date. WHY???

To make things even weirder, if I drag one task that is dependent on another to an earlier date, it forces the tasks ABOVE to move back which doesn’t seem like that should be a thing (aka a subtask is forcing the timelines of higher tasks).

Any thoughts on how I can make this work better?

0 replies

Be the first to reply!