Hello @Sappho_Hansen_Smythe,
Adam from Airtable here. This is definitely possible and, because Airtable is flexible, there are potentially multiple ways to accomplish this.
I created this support article a while back that I believe will help. Admittedly, it can take a second to bring all of the parts together, but let me know if you run into any blockers.
Hello @Sappho_Hansen_Smythe,
Adam from Airtable here. This is definitely possible and, because Airtable is flexible, there are potentially multiple ways to accomplish this.
I created this support article a while back that I believe will help. Admittedly, it can take a second to bring all of the parts together, but let me know if you run into any blockers.
Aw heck yeah! Thank you so much!
Hello @Sappho_Hansen_Smythe,
Adam from Airtable here. This is definitely possible and, because Airtable is flexible, there are potentially multiple ways to accomplish this.
I created this support article a while back that I believe will help. Admittedly, it can take a second to bring all of the parts together, but let me know if you run into any blockers.
Ooh actually I do have one more question. I was able to complete everything in your support article easily (thank you for being so clear! Love it!), but there’s one more thing I’d love to figure out:
Do you know of a way to connect the Calculation field to a Single Status field marking things “Done” and “Not Done”? It would be really cool to be able to see complete & incomplete tasks in a Kanban view as well, especially so my team can see more clearly what has been done already. Something like “if Calculation = Task complete, Status = Done”. Do you know if this is possible?
Ooh actually I do have one more question. I was able to complete everything in your support article easily (thank you for being so clear! Love it!), but there’s one more thing I’d love to figure out:
Do you know of a way to connect the Calculation field to a Single Status field marking things “Done” and “Not Done”? It would be really cool to be able to see complete & incomplete tasks in a Kanban view as well, especially so my team can see more clearly what has been done already. Something like “if Calculation = Task complete, Status = Done”. Do you know if this is possible?
Hi again!
Glad to hear the support article helped!
I’d set up a “When a record matches conditions” trigger in an automation that would update the record’s status field based upon the formula’s output. Essentially, the “logic” would be implemented via the conditions matching in the trigger step.
Then, in a Kanban view, you could use the single-select status field to group the records in a stack.
Does that seem like it would help?
Hi again!
Glad to hear the support article helped!
I’d set up a “When a record matches conditions” trigger in an automation that would update the record’s status field based upon the formula’s output. Essentially, the “logic” would be implemented via the conditions matching in the trigger step.
Then, in a Kanban view, you could use the single-select status field to group the records in a stack.
Does that seem like it would help?
Ugh yes! That’s totally it. Thank you so much, you have a beautiful brain