Hi, 

I’m new to using Airtable. I create a Gantt view when I set up dependencies between some  milestones. 

I noticed  that in my Gantt view when I have  milestone that is dependent on another milestone, even if I move the first milestone it does not affect the milestone that is dependent on it. 

however, when a milestone is dependent on a task that has a duration, the change is reflected.

Milestone 2 depends on Milestone 1 

 

After moving Milestone1 one day later , Milestone 2 remains due for the 25th. I expected it to move 1 day later   

 