How do I add risk management into a project? For example: I have a timeframe, and assign a risk, which gives me a pessimistic and optimistic view of time padded onto the start/end date. I’ve seen this in other tools, where it changes the color, so the center block is assigned, to the left is optimistic, and right is pessimistic.
Page 1 / 1
So to manage the record, you can add a formula that will add # of days on each side based on risk. So a optimistic start and pessimistic end as a formula. That will give you the pad.
Showing up on the Gantt might be a little tricky, perhaps use the Vega block to visualize?
So to manage the record, you can add a formula that will add # of days on each side based on risk. So a optimistic start and pessimistic end as a formula. That will give you the pad.
Showing up on the Gantt might be a little tricky, perhaps use the Vega block to visualize?
Thanks that’s very helpful!