Dec 20, 2024 06:46 AM
Hello,
Our team has reduced available hours in the summer, and I'm trying to figure how to represent this when using the Utilization summary in Timeline view so that their Available Hours are reduced during a set start and end date. Thank you!
Solved! Go to Solution.
Dec 21, 2024 05:36 AM
hmm.. so here's the thing
Airtable's Timeline view's "Utilization" function calculates resource allocation based on time tracked or assigned within a date range, it does not have a built-in feature to adjust available hours based on date ranges. There is no direct setting to input a "reduced hours" schedule that the Timeline view automatically recognizes for resource utilization calculations.
Potential Solution
Create a Formula field that adjusts the "Available Hours" based on the summer hours table you created. This formula will check if the date of the task is within the summer period and if it is, will use the reduced hours, otherwise it will use standard available hours.
Dec 21, 2024 05:36 AM
hmm.. so here's the thing
Airtable's Timeline view's "Utilization" function calculates resource allocation based on time tracked or assigned within a date range, it does not have a built-in feature to adjust available hours based on date ranges. There is no direct setting to input a "reduced hours" schedule that the Timeline view automatically recognizes for resource utilization calculations.
Potential Solution
Create a Formula field that adjusts the "Available Hours" based on the summer hours table you created. This formula will check if the date of the task is within the summer period and if it is, will use the reduced hours, otherwise it will use standard available hours.
Dec 30, 2024 06:37 AM - edited Dec 30, 2024 06:39 AM
Thank you @LetAtuomate48; I've been working on this and have two questions as a follow-up if you have thoughts:
I had a thought to an alternative approach, which was to create a weekly holiday during the summer period which lasts for four hours, which would then reduce everyone's available hours calculated in the Utilization view appropriately, but I haven't been able to figure out how to represent half-day holidays as they seem to only be calculated as full days in AirTable, if that's another viable approach.
Thanks again for your thoughts.